Sign up for our mailing list!

Project Timeline

This project is currently intended to be completed by Winter 2020.

  • Preliminary Engineering: Fall 2018 – Fall 2019
  • Environmental Clearance: Spring 2020 – Summer 2020
  • Design: Summer 2019 – Spring 2020
  • Procurement Support: Spring 2020 – Summer 2020
  • Construction: Fall 2020 – Winter 2020
  • Construction Support: Fall 2020 – Winter 2020
  • Project Closeout: Spring 2021
Project Overview
Timeline
Frequently Asked Questions
Events
Documents
Contact Us
Project Overview
Timeline
Frequently Asked Questions
Events
Documents
Contact Us