Project Timeline

This project is currently intended to be completed by Fall 2021.

  • Preliminary Engineering: Fall 2018 – Fall 2019
  • Environmental Clearance: Spring 2020 – Summer 2020
  • Design: Summer 2019 – Fall 2020
  • Procurement Support: Fall 2020
  • Construction: Summer 2021
  • Construction Support: Summer 2021
  • Project Closeout: Fall 2021